Soal Remidi

Berikut Soal Remidi Pengantar Manajemen Proyek untuk kelas A dan B,dirimvia email dengan nama file RemidiMP_Kelas_NIM.pdf ke email : faizahchan@gmail.com paling lambat tgl 20 Mei 2009.

Question 1

Define scope, schedule, cost, and customer satisfaction. Why are these considered to be constraints?

Question 2

Why is it important to determine the critical path of a project? What happens if activities on this path are delayed? What happens if the activities on this path are accelerated?

Question 3

You work for an IT department of a university. The administrative department of the university has asked you to develop a system to manage the students’ assignment and examination results. The aim is to reduce the administrative cost, therefore requiring users to have direct access to the system.

Identify the sponsor and stakeholders in such a proj ect.